PERT Calculator

Other
0.0(0)

Calculates the expected project duration and variance using optimistic, pessimistic, and most likely time estimates.

How To Use

How to use this calculator

Start with your values, or try a preset.

Step 1

Enter Optimistic Time (a), Most Likely Time (m), and Pessimistic Time (b) in the units shown.

Step 2

Read Variance (V) and Expected Time (E) in the results panel. Results update as you change the inputs.

Step 3

Choose a preset to load an example, then adjust the values for your situation.

Worked Examples

Example calculations

See the inputs and their calculated results.

Short Project

Optimistic Time (a): 1 days; Most Likely Time (m): 2 days; Pessimistic Time (b): 3 days

Variance (V): 0.1111111111 days²; Expected Time (E): 2 days

Medium Project

Optimistic Time (a): 2 days; Most Likely Time (m): 5 days; Pessimistic Time (b): 8 days

Variance (V): 1 days²; Expected Time (E): 5 days

Long Project

Optimistic Time (a): 4 days; Most Likely Time (m): 8 days; Pessimistic Time (b): 12 days

Variance (V): 1.777777778 days²; Expected Time (E): 8 days